Avatara Condominium, Mae Phim Beach.
Building A:
° Tiling works on 2, 3, 4 and 5 floor almost complete.
° Tiling works on 6th floor ongoing.
° Door installation has started.
° Plastering works on 6th floor ongoing.
° Block works on 6th and 7th floor ongoing.
° Electrical and sanitary piping works follows the block works.
Building B:
° Ground works completed.
° Pile cap foundation has started.
° Mobilization of more workers has started.